Modular & Prefabricated Building Installation RAMS: UK Compliance Requirements, Hazard Controls & Method Statement
Ramsgen drafts a site-specific RAMS for modular and prefabricated building installation, covering crane lifts, temporary works, working at height and service connections.
A risk assessment and method statement for modular and prefabricated building installation: pod, cassette and volumetric units. Pre-filled hazards address tandem crane lifts, temporary works stability during touchdown, working at height during connections, and service tie-ins. Controls align with LOLER, BS 7121, the Temporary Works Forum guidance and CDM 2015. Adapt them to your unit specs before exporting.
Modular & Prefabricated Building Installation RAMS: key requirements and controls
CDM 2015 and site-specific RAMS
CDM 2015 requires a RAMS to cover the work as it will be done on this site. The hazards and controls below are typical for modular & prefabricated building installation work and need adapting to the site layout, sequence and team before use.
Ramsgen drafts a site-specific modular & prefabricated building installation RAMS from the project requirements.
Snapshot hazards
- Crane and lifting operations for modules (suspended loads, swing, overturning).
- Work at height on modules/roof edges during landing and bolt-up.
- Instability or collapse of unbraced units/temporary works failure.
- Crush and pinch points during landing, alignment and bolting of modules.
- Live services during electrical/gas/mechanical connections and hot works (fire/arc/pressure).
Critical controls
- Appointed Person RAMS; LOLER/PUWER-compliant equipment; CPCS/NPORS crane crew; defined exclusion zones; wind-speed limits monitored by anemometer.
- Work at height hierarchy: MEWPs/guardrails/scaffolds as collective protection; fall arrest only where necessary with rescue plan and inspected anchors.
- Temporary Works managed to BS 5975: named TWC/TWS, design/checks, propping/anchorage, permit-to-load; verify stability before releasing slings.
- Hands-off alignment: taglines, alignment pins/jacks, clear stop signals and radios; banksman control; keep-out zones for non-essential persons.
- Permit-to-work for services: isolations/LOTO, prove dead before work, competent electricians/plumbers, hot works permit, fire watch and suitable extinguishers.
Permits & references
- Permit to Lift.
- Temporary Works permit/permit-to-load from the TWC.
- Permit to Work at Height.
- Electrical/Gas isolation and energisation permits (LOTO).
- Hot Works permit and fire watch arrangements.
Method sequence
- 1
Pre-start planning: review drawings, module weights/COG, RAMS; brief roles and emergency/rescue arrangements.
- 2
Set up site: establish exclusion zones, traffic routes, laydown areas, welfare, and emergency access; display permits and signage.
- 3
Temporary works: verify foundations, bearings and holding-down bolts; install edge protection/propping; obtain TWC sign-off.
- 4
Mobilise plant: position crane on verified ground with mats/outriggers; inspect slings/shackles/spreaders; function-test radios and anemometer; inspect MEWPs.
- 5
Delivery and inspection: check modules for damage, lifting points certification, marked weight/match lines; confirm sling configuration and rigging plan.
- 6
Trial lift: take up slack, verify balance/COG and clearances; control with taglines; proceed only if wind and radius are within plan limits.
- 7
Land and align: lower onto bearings/pads; maintain hands-off policy; use guides/pins/jacking to tolerance; secure temporarily; release slings when stable and authorised.
- 8
Secure structure: complete bolting/strapping between modules; install temporary bracing; weatherproof joints and install permanent fixings.
- 9
Services and firestopping: under permits, complete electrical/gas/mechanical connections; test/commission; apply firestopping and seals to specifications.
- 10
Inspection and handover: complete QA/ITP records, torque checks, TWC permit-to-load/strike, rectify snags, clean down, demobilise plant and reopen areas.
How to create a site-specific Modular & Prefabricated Building Installation RAMS
To make this a site-specific RAMS, cover each point below:
Site-specific checklist
- 1
Site address, client and principal contractor details.
- 2
Named Appointed Person, Lift Supervisor, Crane Operator and Slinger/Signaller.
- 3
Temporary Works Coordinator/Supervisor and design/check references.
- 4
Crane type/capacity chart, outrigger loadings and ground bearing calculations.
- 5
Module schedule: weights, dimensions, COG and lifting point details.
- 6
Foundation readiness: bearings, bolt patterns, tolerances and datum levels.
- 7
Access/logistics plan: delivery timings, laydown areas, traffic routes and escorts.
- 8
Weather/wind limits, stoppage criteria and re-start checks after delays.
- 9
Emergency arrangements: rescue from height, crane evacuation, nearest A&E and muster points.
- 10
Service connection strategy: isolation points, test/commissioning sequence and certification.
HSE compliance alert
A competent person must review the RAMS against the site before work starts, against the manufacturer's instructions and the temporary works coordinator's requirements.
What Ramsgen produces
Ramsgen drafts a site-specific RAMS from the project requirements and your answers about the site. It includes:
- Project-specific hazards based on your site layout and access constraints
- Emergency plans with routes to the nearest A&E and site-specific assembly points
- Permits, inspections, and quality checkpoints aligned to your schedule
- Branded PDF exports ready for principal contractor submission
Related trades
Other RAMS templates a Modular & Prefabricated Building Installation package often sits alongside.
Useful articles
Guides on modular & prefabricated building installation RAMS and CDM 2015.
Build a RAMS for the site you are on
Ramsgen drafts a site-specific RAMS from this template and exports it as a branded PDF.