Solar PV & Renewables RAMS: UK Compliance Requirements, Hazard Controls & Method Statement
Ramsgen drafts a site-specific solar PV and renewables RAMS for your roof type, DC string layout and DNO conditions, with hazards, controls, method steps, PPE and permits.
A solar PV and renewable energy installations risk assessment and method statement for domestic, commercial and ground-mount arrays. Pre-filled hazards cover DC isolation and arc-flash, working at height on roofs, manual handling of panels, inverter and battery commissioning, and grid-tie isolation. Controls align with MCS standards, BS 7671 and CDM 2015. Adapt them to your system specs before exporting.
Solar PV & Renewables RAMS: key requirements and controls
CDM 2015 and site-specific RAMS
CDM 2015 requires a RAMS to cover the work as it will be done on this site. The hazards and controls below are typical for solar pv & renewables work and need adapting to the site layout, sequence and team before use.
Ramsgen drafts a site-specific solar pv & renewables RAMS from the project requirements.
Snapshot hazards
- Falls from height during roof access, panel placement and work near edges.
- Electric shock or arc from DC strings, inverters and AC circuits during installation/commissioning.
- Fragile or unstable roofs, rooflights and skylights leading to through‑falls.
- Dropped objects and falling materials from roofs/MEWPs to areas below.
- Musculoskeletal injuries from manual handling of panels, rails, inverters or batteries.
Critical controls
- Plan and control work at height: scaffold to TG20:21 or proprietary edge protection, MEWP with trained operator, fall restraint/arrest with inspected anchors, ladders only for short duration; implement rescue plan.
- Electrical safety: isolate and lock‑off supplies (LOTO), prove dead with a calibrated tester, maintain strings open‑circuit and covered, correct MC4‑type terminations, no live working unless justified by risk assessment and controlled.
- Fragile surface controls: survey roof, mark/guard fragile zones and rooflights, use crawling boards/roof ladders, demarcate safe walkways and keep clear of unsupported areas.
- Manual handling: team lifts, panel carriers/suction aids, mechanical lifting (hoist/crane), avoid twisting; stage materials close to point of use.
- Dropped‑object and weather controls: toe‑boards, tool lanyards, debris nets/exclusion zones, secure materials at height, monitor wind/rain/ice and stop work when limits or manufacturer restrictions are exceeded.
Permits & references
- Electrical Isolation/Lock‑Out Tag‑Out Permit to Work.
- Roof access/working at height permit with fragile roof controls specified.
- LOLER/PUWER permit for hoist/crane/MEWP, with evidence.
- DNO G98/G99 application/approval and commissioning notification.
- Traffic management/street works permit where works interface with the public highway.
Method sequence
- 1
Pre‑start: review drawings, design, RAMS and product datasheets; complete site induction and brief the team; verify competencies and equipment inspections.
- 2
Establish access and exclusion zones: install/inspect scaffold or position MEWP; confirm Scafftag/LOLER status; set barriers and signage; agree rescue arrangements.
- 3
Electrical safety set‑up: identify isolation points; apply LOTO to AC supply; confirm absence of back‑feed from any existing PV/battery; test for dead; display warning tags.
- 4
Roof preparation: inspect roof condition; identify/guard fragile areas and rooflights; fix temporary lifelines/anchors if specified; stage rescue kit and housekeeping controls.
- 5
Lifting and logistics: lift rails/panels to roof via hoist/crane; check wind speed; secure loads; keep public/exclusion zones enforced.
- 6
Mounting system: set out and fix rails/brackets to structural members per design; use specified fasteners and sealants; maintain drainage and weatherproofing.
- 7
Module installation: lift, place and fix PV modules; keep strings open‑circuit (use string caps/covers); route and secure DC cabling with UV‑rated clips; maintain polarity and segregation.
- 8
Inverter and balance‑of‑system: mount inverters/isolators/SPDs; make DC/AC terminations; label circuits and isolation points; ensure earthing/bonding and cable management are correct.
- 9
Testing, commissioning and notification: perform BS 7671/MCS tests (continuity, insulation resistance, polarity, earth fault loop, RCD/functional); complete Electrical Installation Certificate and schedules; submit DNO G98/G99 documentation; energise only when authorised.
- 10
Handover and demobilisation: produce as‑builts, O&M manuals and warranties; client demonstration; remove temporary works; clear waste; close permits and sign off RAMS.
How to create a site-specific Solar PV & Renewables RAMS
To make this a site-specific RAMS, cover each point below:
Site-specific checklist
- 1
Project address, client and CDM dutyholders (PC/PD/Contractor).
- 2
Roof type, pitch, condition, identified fragile areas and anchor locations.
- 3
Chosen access method (scaffold/MEWP/ladders) and detailed rescue arrangements.
- 4
Wind limits and weather triggers for stopping work, per equipment/manufacturer.
- 5
Crane/hoist position, ground bearing pressures and exclusion zones.
- 6
Asbestos survey status (especially pre‑2000 buildings) and control measures.
- 7
Isolation points and any existing PV/ESS that could back‑feed; metering and earthing arrangement.
- 8
DNO references (G98/G99), meter location and switchgear details.
- 9
Public interface and traffic/pedestrian management near entrances, schools or retail.
- 10
Environmental constraints: noise hours, bird nesting, runoff control and waste segregation.
HSE compliance alert
A competent person must review the RAMS against the site before work starts. No work on or near live conductors unless it is justified and controlled.
What Ramsgen produces
Ramsgen drafts a site-specific RAMS from the project requirements and your answers about the site. It includes:
- Project-specific hazards based on your site layout and access constraints
- Emergency plans with routes to the nearest A&E and site-specific assembly points
- Permits, inspections, and quality checkpoints aligned to your schedule
- Branded PDF exports ready for principal contractor submission
Related trades
Other RAMS templates a Solar PV & Renewables package often sits alongside.
Useful articles
Guides on solar pv & renewables RAMS and CDM 2015.
Build a RAMS for the site you are on
Ramsgen drafts a site-specific RAMS from this template and exports it as a branded PDF.