Trade RAMS template

Scaffolding risk assessment and method statement: contents and review checks

A site-specific scaffolding RAMS sets out the TG20:21 or bespoke design, ground and ties, erection sequence, public protection and inspection after handover. Ramsgen drafts one from your project documents.

A scaffolding risk assessment and method statement covers the erection, alteration, use and dismantling of one scaffold on one site. Most of a scaffold RAMS has to settle four things: the design or TG20 compliance sheet the scaffold is built to, how the scaffolders are protected while it goes up and comes down, how the public and other trades are protected around it, and who inspects it once it is handed over. Each point cites the regulation or HSE publication it comes from.

Scaffolding risk assessment and method statement template: what goes in it

These are the sections of a scaffolding RAMS for erecting, altering and dismantling a scaffold, and what each one has to cover before a principal contractor will accept it. Ramsgen drafts a site-specific scaffolding RAMS for your scaffold, ground and programme. Draft one free.

Project and scope
Site address, client, principal contractor and the elevations being scaffolded. The scaffold type (independent tied, birdcage, cantilever, temporary roof, chimney or loading tower), whether the work is erection, alteration, adaptation or striking, the dates and duration, and any work out of hours.
Design basis
The TG20:21 compliance sheet reference for a tube and fitting scaffold inside its scope, the manufacturer's guidance for a system scaffold, or the bespoke design drawing and the designer's name for everything else. The load class or duty, the tie pattern, and whether sheeting, netting, brick guards, loading bays or hoists were allowed for in that design.
Temporary works control
Who holds the design brief and the design check, who the temporary works coordinator is, how the scaffold is accepted before loading, and how a request to alter it is made, approved and recorded.
Site survey: ground, structure and services
Ground bearing, base plates and sole boards, and anything underneath that may not take the load: cellars, voids, drains, chambers, soft or sloping ground. What the ties fix into and whether the anchors need testing. Overhead lines, fragile roofs, traffic routes and adjacent property.
Erection, alteration and dismantling sequence
The order the scaffold goes up and comes down, lift by lift. Which SG4:22 method protects the scaffolders at each stage, when ties go in and when they come out, and how an incomplete scaffold is signed and physically closed off.
Materials delivery and lifting
Delivery times, where the wagon stands and where the tube, fittings and boards are stacked. How material reaches each lift (by hand, gin wheel, hoist or crane), the lifting plan where one is needed, and the exclusion zone underneath.
Public and third-party protection
The highway licence where the scaffold stands on or over a highway, pavement closures, fans, tunnels, brick guards and debris netting, lighting at night, padding on tube ends, and how access is closed off out of hours.
Fall protection and rescue plan
Collective protection before personal protection. Where harnesses are used, what they connect to and who checks them. How a scaffolder left suspended in a harness is brought down, by whom, with what equipment, and how long that takes, without relying on the emergency services.
Inspection, handover and tagging
The inspection before first use, every 7 days and after alteration or bad weather. Who inspects, who receives the report, the handover certificate, and the tag at each access point showing whether the scaffold is safe to use.
Weather
The wind, rain, ice and lightning conditions that stop erection and stop use, how wind is measured and who calls the stop. Whether the scaffold is sheeted, and what the design allows for that.
People, competence and PPE
The supervisor by name, the CISRS card each role needs, who is trained in the rescue plan, and task-specific PPE: harness and lanyard where SG4:22 calls for them, helmets with chin straps, gloves and safety footwear.
Emergency arrangements, briefing and sign-off
Nearest hospital, first aiders, how the alarm is raised, how the crew is briefed and how that is recorded, and the document's revision, date and approval.

What this work involves on a real site

Design basis

The Work at Height Regulations require strength and stability calculations for a scaffold unless it is built to a generally recognised standard configuration. For tube and fitting that usually means a TG20:21 compliance sheet. For a system scaffold it means the manufacturer's guidance. For a birdcage, a cantilever, a temporary roof or anything outside those limits it means a bespoke design by a competent person. The RAMS must state which of these applies, with the compliance sheet or design reference.

Ground and footings

Base plates and sole boards spread the load, but cellars, drains, inspection chambers and soft ground under a footway may not take it, and ground that is firm when dry can soften after rain. HSG150 warns that excavations by other trades can undermine scaffold footings.

Ties and anchors

Through ties pass through window openings the window fitters want back. Drilled anchors go into masonry that may not hold them, and in a building completed before 2000 they may go into material that contains asbestos. HSG150 names ties forgotten, or removed too early during striking, as a cause of scaffold collapse.

Erection, alteration and dismantling

During erection, alteration and dismantling the scaffolders work at an edge the scaffold does not yet protect, or no longer protects. NASC SG4:22 sets out the methods that keep a guard-rail ahead of them, such as advance guard-rail systems. The RAMS has to say which method is used on which part of this scaffold, and where a harness is still needed.

Public protection

A scaffold that stands on or over a highway needs a licence from the highway authority, lighting at night and protection from falling material: fans, tunnels, brick guards, netting, or close or double boarding over the footway. HSG150 says scaffolds should never be erected or dismantled over people or busy pavements, which means a road or footway closure, or a segregated area at quiet times.

Loading and sheeting by other trades

Bricklayers stack on it, roofers store tiles at eaves level, and somebody asks for sheeting or a rubbish chute after it is up. Each one adds load or wind area the design may not have allowed for. HSG150 says to assume a general purpose scaffold at 2 kN/m² unless the provider says otherwise, and never to sheet or net a scaffold without telling the supplier.

Inspection after handover

Once the scaffold is handed over, the scaffolders leave and other trades work from it for weeks. The 7-day inspections, the inspection after high winds and the inspection after an alteration all fall in that period. The RAMS has to say who carries them out after handover, and who receives the report.

Questions to answer before writing the RAMS

Each answer depends on the site and the job. A site-specific RAMS answers every one.

Design and configuration

  • Is this scaffold inside a TG20:21 standard configuration or the system manufacturer's guidance, or does it need a bespoke design?
  • What is the compliance sheet or design drawing reference, its revision, and who produced it?
  • What load class or duty does the work need, and does the design match it?
  • Does the design allow for the sheeting, netting, brick guards, loading bays, hoists or chutes the job will add?
  • Who is the temporary works coordinator, and what do they need to see before the scaffold is loaded?

Ground, structure and services

  • What is under each standard: slab, footway, soft ground, a cellar, a drain run, a chamber?
  • Is the ground level, and if it slopes, how is that taken up?
  • What do the ties fix into, and if they are drilled anchors, who tests them and how many?
  • Does the asbestos survey cover the places anchors or through ties will go?
  • Is any part of the scaffold, or the route the tube is carried along, within 10 m of an overhead line measured horizontally at ground level?
  • Is there a fragile roof, roof light or glazed canopy the scaffold is built over or next to?

Erection, alteration and dismantling

  • Which SG4:22 method protects the scaffolders on each lift, and where is a harness still needed?
  • When is each tie fitted during erection, and in what order do ties come out during striking?
  • How is an incomplete scaffold closed off at the end of each shift, and at each access point?
  • Who may alter the scaffold after handover, and how does another trade ask for an alteration?
  • Where a tie or a guard-rail must come out for another trade, what replaces it, and who checks?

Materials, loading and lifting

  • Where does the wagon stand, and how long is the footway or road taken up while it unloads?
  • How does material reach each lift, and does that need a lifting plan?
  • Where are the loading bays, what load are they designed for, and how is the safe working load shown?
  • How many lifts will be loaded at once, and does the design allow it?

The public and other trades

  • Does the scaffold stand on or over a highway, and has the licence been applied for?
  • Can erection and striking happen with the footway closed, or at quiet times inside a segregated area?
  • Which protection does the footway need: fans, a tunnel, double boarding, netting, lighting, padding?
  • How are ladders removed or boarded at the end of the day, and can anyone reach the scaffold from inside the building through an upper window?
  • Which other trades will work from the scaffold, and who tells them what it is designed to carry?

Inspection, weather and rescue

  • Who inspects the scaffold before first use, every 7 days, and after alteration or bad weather, and who receives the report?
  • Where is the tag at each access point, and who updates it?
  • At what wind conditions does erection stop, and at what conditions does use stop? Who measures, where, and with what?
  • If a scaffolder falls and is left hanging in a harness, who brings them down, with what equipment, and how long will it take?
  • Who is trained in that rescue, and when was it last practised?

People

  • Who is the supervisor on site, by name, and what CISRS card do they hold?
  • Which operatives are trainees, and who are they working under?
  • Who briefs the crew on this scaffold's sequence, tie pattern and rescue plan, and how is that recorded?

Hazards commonly left out of this trade's RAMS

Generic RAMS cover slips, trips and manual handling but often leave out the hazards particular to the job. The hazards below are the ones most often missing for this trade.

Ties removed by other trades
The window fitter needs the opening, the cladder needs the face, and the tie is in the way. The RAMS was written for the scaffold on the day it was handed over, and nothing in it says what happens when somebody else asks for a tie to come out. The RAMS must say who approves a tie removal, what replaces it and who checks it.
Sheeting, netting and added loads
Sheeting goes up for the winter, a brick guard is added, roof tiles are stacked at eaves level, a chute is hung off the side. Each is a small request on site, and none of them prompts a change to a document that has already been accepted. HSG150 says never to sheet or net a scaffold without informing the supplier, because the design has to allow for the wind load.
Ground changes after erection
The ground survey happens before erection and is not repeated. A drainage trench beside the footings, a utility dig in the footway, or a week of rain changes what the base plates stand on. HSG150 warns against excavations undermining scaffold footings, and the inspection after bad weather is the only routine check that looks for it.
Rescue of a suspended scaffolder
The rescue section says call 999 and the hazard row says falls from height, so the document looks complete. The Work at Height Regulations require planning for emergencies and rescue, and INDG401 says not to rely entirely on the emergency services. The rescue plan must name the rescuer, the equipment and the method.
Overhead lines over the delivery route
Hazard lists are built from the scaffold, and the scaffold is against the building. The line is over the road where the wagon unloads and the tube is carried. GS6 names scaffold tubes among the equipment involved in overhead line contact, and its 10 m planning distance applies to the route as well as to the scaffold.
Out-of-hours access
HSG150 asks for ladders to be removed at ground level when nobody is on site, and points out that during refurbishment the scaffold can also be reached from inside the building through an upper window. The second route is easy to miss because it is not on the scaffold drawing.
Inspection after the scaffolders leave
The scaffold contractor inspects at handover, and the RAMS often stops there. The 7-day inspections and the inspections after high winds happen while other trades are using the scaffold. If no document names who carries them out, each party can assume the other does.

Thresholds and triggers

The figures that set a duty or a control for this work, each with the publication it comes from.

Inspection and records

2 m or more, and 7 daysInspection of a working platform used for construction work

A working platform from which a person could fall 2 metres or more must not be used in any position unless it has been inspected in that position within the previous 7 days. A scaffold must also be inspected after assembly and before first use, and again after any exceptional circumstance liable to jeopardise its safety. HSG150 gives the practical triggers: after alteration, damage and extreme weather.

Work at Height Regulations 2005, regulation 12(2) to (4); HSG150, Health and safety in construction

Under 2 mPlatforms below the 7-day trigger

The 7-day rule stops applying, but the duty to inspect does not. HSG150 asks for inspection at suitable intervals where the platform is under 2 m, and the duties to inspect after assembly and after anything affecting safety still apply.

HSG150; Work at Height Regulations 2005, regulation 12(2) and (3)

End of the shift, and 24 hoursWriting up and handing over the inspection report

The person who inspects a working platform covered by the 7-day rule must prepare the report before the end of the working period in which the inspection was completed, and provide it, or a copy, within 24 hours to the person the inspection was carried out for.

Work at Height Regulations 2005, regulation 12(7)

On site to completion, then 3 monthsKeeping the inspection report

The employer who receives the report keeps it, or a copy, at the site until the construction work is completed, and then at an office for 3 months.

Work at Height Regulations 2005, regulation 12(8)

8 particularsWhat an inspection report must contain

Who the inspection was for, the location, a description of the equipment, the date and time, anything found that could give rise to a risk, the action taken, any further action needed, and the name and position of the person making the report. A tag at the access point does not carry all of this, so a tag on its own is not the report.

Work at Height Regulations 2005, Schedule 7

Every 7 daysLadders that form part of a scaffold system

HSG150 says ladders that are part of a scaffold system must be inspected every seven days. Ladders also need a pre-use check each working day.

HSG150

Guard-rails and toe-boards

950 mmHeight of the top guard-rail in construction work

The top guard-rail, or other similar means of protection, must be at least 950 mm above the edge from which a person could fall.

Work at Height Regulations 2005, Schedule 2, paragraph 3

470 mmLargest unprotected gap between guard-rails and toe-board

An intermediate guard-rail, or similar, must be positioned so that no gap between it and the other means of protection exceeds 470 mm. A top guard-rail and a toe-board alone leave a gap well over that, which is why every working lift needs an intermediate rail.

Work at Height Regulations 2005, Schedule 2, paragraph 3

Suitable and sufficientToe-boards, and material stacked above them

The Regulations set no height for a toe-board: it must be suitable and sufficient to stop people, materials and objects falling. HSG150 says not to stack material above the toe-board unless brick guards or another means of retaining it are in place, and to tie down boards if high winds are possible.

Work at Height Regulations 2005, Schedule 2, paragraph 3; HSG150

Design and loading

Standard configuration, or calculationsWhen a scaffold needs a design

Strength and stability calculations are required unless a note of calculations covering the arrangement is available, or the scaffold is assembled to a generally recognised standard configuration. HSG33 names NASC TG20 for tube and fitting scaffolds and the manufacturer's guidance for system scaffolds. Anything else is designed by a competent person.

Work at Height Regulations 2005, Schedule 3, Part 2, paragraph 7; HSG33, Health and safety in roof work

0.75, 2 and 3 kN/m²Duty ratings: inspection and very light duty, general purpose, heavy duty

HSG150 says to assume a scaffold is general purpose, 2 kN/m², unless the provider says otherwise. An inspection and very light duty scaffold is 0.75 kN/m² and a heavy duty scaffold 3.0 kN/m². Anyone intending to load out platforms has to tell the provider, and a special design is likely.

HSG150

600 mmWidth of a working platform

Before a scaffold is used, platforms should be fully boarded and wide enough for the work and for access, usually at least 600 mm.

HSG150

4 times the board thicknessBoard overhang

Scaffold boards must be properly supported and must not overhang excessively. HSG150 gives no more than four times the thickness of the board as the example.

HSG150

Personal fall protection

6 months, and 3 months in scaffoldingDetailed inspection of a webbing or rope lanyard

INDG367 recommends a recorded detailed inspection at least every six months, increased to at least every three months for frequently used lanyards in arduous environments, and names scaffolding as one. This is in addition to the user's pre-use check. A lanyard with no evidence of inspection by a competent person within six months is withdrawn from use and passed to a competent person.

INDG367, Inspecting fall arrest equipment made from webbing or rope

Overhead lines

10 mThe distance within which the risk has to be managed

GS6: manage the risks if you intend to work within 10 m of an overhead line, measured at ground level horizontally from below the nearest wire. GS6 names scaffold tubes and ladders among the equipment involved in contact, and electricity can arc across a gap without the wire being touched.

GS6, Avoiding danger from overhead power lines

1 m at low voltage, 3 m at 11 kV and 33 kV, 6 m at 132 kV, 7 m at 275 kV and 400 kVExclusion zones around the line

No part of plant or equipment, including ladders, poles and hand tools, may encroach into these zones. GS6 says to carry long objects horizontally and close to the ground, and to allow for uncertainty in measuring the distance and for movement in wind.

GS6, citing ENA, Look Out Look Up!

Existing buildings

Before 2000The age of the building that decides the asbestos presumption

Premises whose construction was completed before 2000 should be presumed to contain asbestos unless there is strong evidence otherwise. That matters wherever anchors are drilled or ties are fixed into the existing fabric.

L143, Managing and working with asbestos

The highway

Half an hour after sunset to half an hour before sunriseLighting a licensed scaffold on a highway

In England and Wales, scaffolding on or over a highway that obstructs it needs a licence from the highway authority, and the licence holder must keep the scaffold adequately lit between these times.

Highways Act 1980, section 169(1) and (4)

Legislation and guidance

WAHR 2005Work at Height Regulations 2005, with INDG401
The duties behind most of this page. Regulation 4 requires work at height to be planned, including for emergencies and rescue, and carried out only when the weather does not put people at risk. Regulation 12 sets the inspection and report regime. Schedule 2 sets guard-rail heights and gaps. Schedule 3 Part 2 covers scaffolding: calculations or a standard configuration, an assembly, use and dismantling plan, signs and physical barriers on an incomplete scaffold, and erection, dismantling and significant alteration only under the supervision of a competent person, by people with appropriate training.
CDM 2015Construction (Design and Management) Regulations 2015, with guidance in L153
Regulation 19 requires any temporary structure to be designed, installed and maintained to withstand the foreseeable loads, used only for the purpose it was designed for, and not loaded so as to make it unsafe. CDM also makes the principal contractor the reader this document has to satisfy.
NASC TG20:21Guide to good practice for scaffolding with tubes and fittings
The standard configurations for tube and fitting scaffolds, and the compliance sheet that records a scaffold is inside them. Outside its scope, the scaffold needs a bespoke design.
NASC SG4:22Preventing falls in scaffolding operations
The industry guidance on protecting scaffolders from falls while erecting, altering and dismantling, including advance guard-rail methods, the use of personal fall protection, and rescue.
BS 5975Code of practice for temporary works procedures and the permissible stress design of falsework
How temporary works, scaffolding included, are managed: the design brief, the design check, the temporary works coordinator, and permission to load and to dismantle.
BS EN 12811-1Temporary works equipment. Scaffolds. Performance requirements and general design
The standard behind scaffold load classes and platform design. TG20 configurations are designed to it, and system scaffolds are designed to it together with BS EN 12810.
HSG150Health and safety in construction
HSE's general construction guidance on scaffolds: foundations and ties, duty ratings, checks before use, inspection frequency, sheeting, falling materials and protecting the public.
HSG33Health and safety in roof work
Scaffolds for roof work: eaves platforms, brick guards, loading bays designed for the actual load with the safe working load displayed, temporary roofs, and rescue after a fall is arrested.
INDG367Inspecting fall arrest equipment made from webbing or rope
Pre-use checks, and detailed and interim inspections of lanyards, and when to withdraw one. Scaffolding is named as an arduous environment needing more frequent inspection.
GS6Avoiding danger from overhead power lines
Any scaffold, delivery or tube handling near an overhead line: the 10 m planning distance, barriers, and exclusion zones by voltage.
Highways Act 1980, s169Control of scaffolding on highways
In England and Wales, a licence from the highway authority for scaffolding on or over a highway that obstructs it, and the duty to keep it lit at night.
LOLER 1998Lifting Operations and Lifting Equipment Regulations 1998, with L113
Gin wheels, hoists and cranes used to raise scaffold materials: planning of lifts, thorough examination, and the safe working load of the equipment.

What a reviewer checks

Ramsgen's RAMS review runs these checks in this order. Each lists the condition that fails it and its minimum severity. Write the RAMS to pass them.

Stage 1

Is the scope correct?

  • Every site-identifying fact belongs to this project: address, postcode, client, principal contractor, elevations, compliance sheet or design reference, highway authority, hospital, emergency contacts.

    critical

    Not a pass if: A recorded fact traces to a different site or job, or cannot be reconciled with the project's own documents. For example, a TG20 compliance sheet or design drawing for another address or elevation.

  • The task this document describes is the task the project asked for.

    critical

    Not a pass if: They are different work. A method for an independent tied scaffold, submitted for a temporary roof or a cantilever, fails this check.

  • The dates and duration here and in the project programme can both be true.

    minor

    Not a pass if: A recorded date or duration cannot be reconciled with the programme, or precedes the document's own issue date.

  • Nothing the project requires is work this document declines to cover.

    major

    Not a pass if: The project requires work the document excludes, so nothing covers it. For example, alterations and adaptations for later trades, left out of a document that covers erection and striking only.

  • The document does not claim scope the project did not give it.

    major

    Not a pass if: It asserts work it was not given, or authority over work another party holds. For example, approving its own design where the project gives that to the temporary works coordinator.

  • Where the document states its scope more than once, the restatements agree.

    major

    Not a pass if: Two restatements disagree: a load class one way in the summary and another in the method, a scaffold height that changes between the drawing and the text, a supervisor named differently in two places.

Stage 2

Has the risk been assessed?

  • The register assesses every hazard, substance and regulation the document names anywhere in itself, including in the control cells of the register.

    major

    Not a pass if: Something the document names has no row. Sheeting, a hoist or a gin wheel mentioned only in another row's controls fails this check: if the document controls it, it needs its own row.

  • Each score follows the document's own stated convention.

    minor

    Not a pass if: The arithmetic does not follow the convention the rest of the table establishes, the residual score equals the initial one, or a column holds the same value across hazards of different kinds.

  • For each row, the control hierarchy meets the harm the row itself names.

    major

    Not a pass if: A hazard is held up by nothing but PPE, administration and behaviour where collective protection is reasonably practicable. For example, a falls row for erection controlled by harness and supervision alone, with no advance guard-rail method considered.

Stage 3

Does the plan reflect the risks identified?

  • The method carries out every control the assessment relies on.

    major

    Not a pass if: A control the register counts on has no step. A register that relies on ties fitted as erection proceeds, with no tie step in the method until the scaffold is complete, fails this check.

  • The assessment covers every step the method plans.

    major

    Not a pass if: The method performs work no row assesses: a loading bay, a pavement lift, a hoist, a chute or a crane lift that appears in the sequence and nowhere in the register.

  • Each control appears before the step that needs it.

    major

    Not a pass if: The control comes after. Guard-rails fitted once the lift is boarded and worked from, or ties taken out before the lift above them is struck, are this.

  • Each control names a person and a trigger, so somebody could carry it out as written.

    minor

    Not a pass if: Hedged wording such as "weather to be monitored", "inspections as required" or "ties where possible" fails this check. A control nobody is assigned and nothing triggers cannot be carried out, and the residual score rests on it.

  • Where a control is that somebody will be rescued, the arrangement named exists and works.

    major

    Not a pass if: It is unnamed, unworkable, or resourced by people this document does not provide. A rescue plan for a suspended scaffolder that says the emergency services will be called is a rescue plan that does not exist.

What principal contractors check in a RAMS

Why Scaffolding RAMS get rejected

No design reference
Built to TG20 with no compliance sheet number, or a birdcage, cantilever or temporary roof with no design drawing. The reviewer cannot check the scaffold against anything, and cannot tell whether the loading, sheeting and ties in the method are inside what the design allows.
SG4 named, method not described
SG4:22 will be followed, with no statement of which method protects the scaffolders on which lift. The reviewer needs to see the advance guard-rail system or other method, where it is used, and where a harness is still needed.
Rescue plan relies on 999
Call 999, or a reference to a rescue plan that is not attached. The Work at Height Regulations require planning for rescue, and a suspended scaffolder needs somebody on site with the equipment and training to bring them down.
No inspection after handover
The scaffold is inspected before handover and the document says nothing after that. The 7-day inspections and the inspections after alteration and bad weather need a named person, and a report going to a named recipient.
Generic public protection
Barriers and signage as required, on a scaffold that stands over a busy footway. The reviewer expects the highway licence, the closure or segregation for erection and striking, and the fans, tunnel, netting or boarding this footway needs.
Sheeting or loading bays outside the design
The method sheets the scaffold or builds a loading bay, and the design or compliance sheet referenced does not allow for either. The reviewer reads that as an overloaded scaffold on paper.
Details from a different job
The address, the elevations, the compliance sheet or the hospital carried over from the last submission.
Controls with no person or trigger
Weather to be monitored, inspections as required, ties where possible. A control with no person and no trigger cannot be checked on site, and the residual score is resting on it.

Before this goes on site

A competent person must assess each scaffold before work starts, under the Work at Height Regulations 2005, CDM 2015 and the design or standard configuration the scaffold is built to. A scaffold outside a standard configuration needs calculations before it is built, and the rescue plan has to work without the emergency services.

Common questions

What goes in a scaffolding risk assessment?

The scope and scaffold type, the design basis (a TG20:21 compliance sheet, the system manufacturer's guidance, or a bespoke design), the site survey of ground, ties and overhead lines, the erection and dismantling sequence with the SG4:22 method used, materials handling, public protection, the rescue plan, the inspection and handover arrangements, weather limits, and the people and their CISRS cards. The template section above sets out what each part covers.

Is a TG20 compliance sheet the same as a scaffold design?

No. A TG20:21 compliance sheet records that a tube and fitting scaffold falls inside one of TG20's standard configurations, which is what allows it to be built without its own calculations. A scaffold outside that scope, such as a birdcage, a cantilever, a temporary roof or loading beyond the configuration, needs a bespoke design by a competent person. System scaffolds follow the manufacturer's guidance instead.

How often must a scaffold be inspected?

After it is assembled and before first use, then within every 7 days where a person could fall 2 metres or more, and after anything liable to affect its safety: an alteration, damage, a vehicle strike, high winds or extreme weather. The inspector writes a report before the end of the shift and provides it within 24 hours. The report is kept on site until the work is complete, and then for 3 months.

Who can inspect a scaffold?

A competent person: somebody with the training, knowledge and experience to judge whether this scaffold is safe for its intended use. For anything beyond a simple scaffold that usually means a scaffold inspection qualification, such as the CISRS scaffold inspection courses, or manufacturer training for a particular system. The RAMS should name who inspects after handover, not only at it.

Is a scaffold tag a legal requirement?

The legal requirement is the inspection and its written report, with the particulars in Schedule 7 of the Work at Height Regulations. A tag at each access point is the common way of showing users whether the scaffold is safe to use and when it was last inspected. HSG150, discussing tower scaffolds, describes a visible tag system as a way to supplement inspection records, not replace them.

What is a scaffold handover certificate?

The document the scaffold contractor issues when the scaffold is handed over for use. It records what was built and where, the load class or duty, the design or compliance sheet it was built to, and any restrictions on use. It is the starting point for the inspections that follow, not a substitute for them.

What goes in a rescue plan for working on scaffolding?

Who carries out the rescue, the equipment they use and where it is kept, the method for bringing down a scaffolder suspended in a harness, how quickly that can be done, and who has been trained and when it was last practised. The Work at Height Regulations require planning for rescue, and INDG401 says the plan should not rely entirely on the emergency services. HSG33 says to call an ambulance for anyone who becomes unconscious while suspended, even if they appear to recover.

Can a scaffold be sheeted or netted after it is up?

Only if the design allows for it. Sheeting and netting add wind load, and HSG150 says never to sheet or attach debris netting to a scaffold without telling the supplier, because they need to make sure the scaffold is designed for it. Brick guards add wind load too, and the design has to account for them.

What does a scaffold loading bay need?

A design for the actual weight of the materials placed on it, with an allowance for impact loads from mechanical handling such as a crane or forklift, and a notice showing its safe working load (HSG33). HSG150 adds that loading bays need fall protection, preferably gates that can be moved in and out of position while materials are placed.

Do we need a licence for scaffolding on the pavement?

In England and Wales, yes, where the scaffold stands on or over a highway and obstructs it: section 169 of the Highways Act 1980 requires a licence from the highway authority, and the scaffold must be kept lit at night. Separately, HSG150 says scaffolds should not be erected or dismantled over people or busy pavements, so the RAMS should say how the footway is closed or segregated while that happens.

At what wind speed should scaffolding work stop?

There is no single figure in the Regulations. Regulation 4 requires work at height to be carried out only when the weather does not jeopardise the people doing it. The figure comes from the scaffold design, the system manufacturer and the contractor's own procedure. The RAMS should state it, how and where wind is measured, and who calls the stop. A sheeted scaffold catches more wind and must be designed for that load.

Do scaffold users need to wear a harness?

Not on a fully boarded and guarded scaffold that is already up and is not being altered or taken down: INDG401 gives that as an example where personal fall arrest equipment is not needed as well. Scaffolders erecting, altering and dismantling are in a different position, and SG4:22 sets out the methods and the personal fall protection used then.

What CISRS card does each person need?

The card for the role they are doing, from labourer and trainee scaffolder through scaffolder and advanced scaffolder to supervisor, with trainees working under the supervision of a qualified scaffolder. The Work at Height Regulations allow scaffolding to be erected, dismantled or significantly altered only under the supervision of a competent person by people with appropriate training, and CISRS cards are how the industry evidences that.

What does the principal contractor check in a scaffold RAMS?

Three questions in order: is the scope correct, has the risk been assessed, and does the plan reflect the risks identified. The checks under each are set out above, with the clause that fails them. For scaffolding the common failures are a missing design reference, a rescue plan that relies on 999, and inspections that stop at handover.

Related trades

Trades that often work alongside scaffolding.

Build a RAMS for the site you are on

Ramsgen records these considerations for your job, including what was ruled out and why.

Your first RAMS is free.

Plan a site-specific, CDM 2015 compliant safe system of work for your job.

No card needed. Full terms.