Trade RAMS template

Piling & Deep Foundations RAMS: UK Compliance Requirements, Hazard Controls & Method Statement

Ramsgen drafts a site-specific piling and deep foundations RAMS for your rig, bore depths and buried services under the working platform, with hazards, controls, method steps, PPE, training and permits.

A piling and deep foundations risk assessment and method statement for CFA, driven, secant and sheet piling works. Pre-filled hazards cover plant-pedestrian segregation, rig stability, noise and vibration affecting neighbours, spoil management and obstructions. Controls align with HSE guidance, BS 8004, BS EN 12699 and CDM 2015. Adapt them to your rig spec and ground conditions before exporting.

Piling & Deep Foundations RAMS: key requirements and controls

⚠

CDM 2015 and site-specific RAMS

CDM 2015 requires a RAMS to cover the work as it will be done on this site. The hazards and controls below are typical for piling & deep foundations work and need adapting to the site layout, sequence and team before use.

Ramsgen drafts a site-specific piling & deep foundations RAMS from the project requirements.

Snapshot hazards

  • Piling rig overturning/instability due to inadequate or failed working platform, soft spots or excessive slope.
  • Striking buried or overhead services during probing, drilling or lifting operations.
  • Entrapment/struck‑by within slew zones, around rotating augers and during crane lifts.
  • Collapse of bore/excavation or falls into open piles; drowning/asphyxiation in support fluids.
  • Environmental and health exposures: noise/vibration, dust and fumes, wet concrete/alkali burns, contaminated spoil and slurry spills.

Critical controls

  • Provide a designed and maintained working platform with verified bearing capacity (FPS Working Platform Certificate), edge protection and daily inspections; no piling off unverified ground.
  • Use competent, authorised personnel: CPCS piling rig operators, appointed person and slinger/signaller; PUWER/LOLER compliant plant with in‑date thorough examinations and pre‑use checks; manufacturer's limits observed.
  • Establish exclusion zones and traffic management; banksman control; slew/height restrictors; interlocked guards and lock‑out for maintenance; clear communications (radios/hand signals).
  • Manage services: review surveys and as‑builts, CAT & Genny scan and trial holes, permits to dig/lift, safe clearances to overhead lines, and immediate stop if unknown service is suspected.
  • Control environmental and health risks: noise/vibration limits and monitoring, dust suppression, spill kits and silt controls, slurry/waste classification and disposal route, COSHH for concrete/support fluids, and a rescue plan for falls into bores.

Permits & references

  • Permit to dig/excavate (service avoidance)
  • Permit to lift/crane operations and rig assembly
  • Working Platform Certificate (FPS) for piling rigs
  • Permit to work near overhead lines/restricted zones
  • Environmental consents (e.g., dewatering discharge, Section 61 noise)

Method sequence

  1. 1

    Pre‑start: review pile design, geotechnical report and RAMS/TW approvals; brief team (inductions and toolbox talks).

  2. 2

    Working platform: install to design, verify via FPS WPC, inspect and sign off; demarcate edges, stockpiles and access routes.

  3. 3

    Utilities: review service drawings, carry out CAT & Genny scan and trial holes; issue permit to dig/lift and mark exclusion zones.

  4. 4

    Deliveries and set‑up: receive rig/crane, assemble as per manufacturer; LOLER checks; set slew/height limits; establish barriers and banksman control.

  5. 5

    Setting out: survey and mark pile positions; verify tolerances; install guide walls or temporary casings where required.

  6. 6

    Drilling/boring: advance pile using specified method (CFA/rotary/driven); maintain verticality; control spoil; use support fluid or temporary casing to prevent collapse as designed.

  7. 7

    Reinforcement: lift and place cages with certified accessories; fit spacers/cover; fix continuity bars/plunge columns as specified.

  8. 8

    Concreting: place via tremie/pump in continuous pour; monitor pressures/volumes; take cubes; progressively extract temporary casings.

  9. 9

    Finishing: trim pile heads safely, cap or connect as required; secure/recover casings; clear arisings and manage slurry/washout.

  10. 10

    QA and close‑out: complete pile records (depth, volumes, tests), concrete tickets and as‑builts; inspect platform condition; demobilise plant and sign off.

How to create a site-specific Piling & Deep Foundations RAMS

To make this a site-specific RAMS, cover each point below:

Site-specific checklist

  • 1

    Pile type/diameter/depth and design loads for this project.

  • 2

    Rig model, operating weight and outrigger/track loadings.

  • 3

    Working platform design values (CBR/thickness), inspection frequency and maintenance plan.

  • 4

    Adjacent structures, vibration criteria and monitoring locations.

  • 5

    Utility constraints, clearances and any planned isolations.

  • 6

    Groundwater level, dewatering method and discharge location/permit.

  • 7

    Crane positions, delivery routes and laydown/stockpile areas.

  • 8

    Noise/time restrictions and Section 61 status.

  • 9

    Spoil/slurry classification, EWC codes and disposal route (on/off site).

  • 10

    Emergency arrangements (rescue from bores), nearest A&E and specific rescue equipment.

HSE compliance alert

A competent person must review the RAMS against the site before work starts, against the design and the ground conditions.

What Ramsgen produces

Ramsgen drafts a site-specific RAMS from the project requirements and your answers about the site. It includes:

  • Project-specific hazards based on your site layout and access constraints
  • Emergency plans with routes to the nearest A&E and site-specific assembly points
  • Permits, inspections, and quality checkpoints aligned to your schedule
  • Branded PDF exports ready for principal contractor submission

Related trades

Other RAMS templates a Piling & Deep Foundations package often sits alongside.

Build a RAMS for the site you are on

Ramsgen drafts a site-specific RAMS from this template and exports it as a branded PDF.

Your first RAMS is free.

Plan a site-specific, CDM 2015 compliant safe system of work for your job.

No card needed. Full terms.