Concrete Works RAMS: UK Compliance Requirements, Hazard Controls & Method Statement
Ramsgen drafts a site-specific concrete works RAMS for your pour, with hazards, controls and a method statement aligned with HSE guidance.
A concrete works risk assessment and method statement covering pours, pumping, formwork strikes and finishing. Pre-filled hazards address skin contamination from wet concrete, manual handling, vibration and noise. Controls map to HSE guidance and CDM 2015 expectations. Adapt them to your mix, pour volumes and access, then export to PDF for the principal contractor before mobilisation.
Concrete Works RAMS: key requirements and controls
CDM 2015 and site-specific RAMS
CDM 2015 requires a RAMS to cover the work as it will be done on this site. The hazards and controls below are typical for concrete works work and need adapting to the site layout, sequence and team before use.
Ramsgen drafts a site-specific concrete works RAMS from the project requirements.
Snapshot hazards
- Skin and eye exposure to wet cement causing alkali burns and dermatitis.
- Manual handling injuries from moving formwork, rebar, tools and cement bags.
- Respirable crystalline silica (RCS) from cutting/grinding concrete or handling dry cement.
- Struck-by/crushing risks from mixers, pumps, vibrators and delivery vehicles (including hose/line failure).
- Formwork/ground instability leading to collapse, falls or impalement on protruding rebar.
Critical controls
- COSHH controls for cement: alkali-resistant gloves, goggles/face shield, barrier cream, eyewash and adequate welfare; no bare-skin contact; prompt decontamination of splashes.
- Dust control: pre-wet materials, water suppression and/or on-tool extraction when cutting; FFP3 RPE (face-fit tested); avoid dry sweeping—use M-class vacuums/wet methods.
- Manual handling: plan lifts, use mechanical aids (telehandler, pump/skip), team lifts for heavy/awkward items; set weight limits; keep routes level, clear and well lit.
- Temporary works and rebar safety: formwork to an approved design with inspections by a TWS/TWC; rebar caps on protrusions; edge protection and exclusion zones maintained.
- Traffic and plant: segregated pedestrian/vehicle routes with a trained banksman; pumps/cranes on verified load-bearing ground with mats; hose whip restraints/pressure checks; lined washout areas and spill control.
Permits & references
- Permit to Pour/Concrete Pour Authorisation (principal contractor).
- Temporary Works Permit/Design approval for formwork and falsework.
- Permit to Dig/Service avoidance (where excavation or anchors are involved).
- Plant/LOLER permit for pumps, cranes or skips as required.
- Approved COSHH assessments for cement, admixtures and washout management.
Method sequence
- 1
Pre-start: review drawings/specs and RAMS; brief the team; confirm Permit to Pour and COSHH; locate/mark services (CAT & Genny) and agree exclusion zones.
- 2
Set up site: barriers, signage and traffic plans; verify safe access/egress, lighting and emergency arrangements; establish lined washout area and spill kits.
- 3
Inspect foundation/sub-base and temporary works: check bearing strata, shutter tightness, ties/props and edge protection; record inspections.
- 4
Fix reinforcement to drawings: place spacers/chairs for cover; secure mesh/bars; fit rebar caps; install cast-in items and check dimensions/levels.
- 5
Plant and materials: inspect pump/mixer, hoses and vibrators; verify calibration/tags; agree delivery schedule and test plan (slump/cubes).
- 6
On delivery: receive and check ticket (mix, slump, additives); carry out slump test and make test cubes as specified; only competent person authorises adjustments.
- 7
Place concrete in layers at a controlled rate; banksman guides pump/skip; avoid free-fall >1.5 m or onto reinforcement; maintain exclusion zone and housekeeping.
- 8
Compact and level using poker vibrators and screeds; avoid over‑vibration/segregation; strike off to datum and check finish tolerances.
- 9
Finish and protect: apply specified finish; commence curing immediately (compound, sheeting or insulation); protect from weather, traffic and contamination.
- 10
Post-pour: monitor curing/temperatures; cut joints to specification; strip formwork only after required strength and TWC approval; remove waste/washout to authorised facilities and reinstate area.
How to create a site-specific Concrete Works RAMS
To make this a site-specific RAMS, cover each point below:
Site-specific checklist
- 1
Concrete element description and location (e.g., ground slab, wall, foundation).
- 2
Mix design, target slump and total volume (m³); supplier and delivery schedule.
- 3
Placement method (pump/skip/direct) and pour sequence/lanes.
- 4
Curing method and duration; temperature monitoring requirements.
- 5
Joint layout, timing and cutting method; saw type and dust controls.
- 6
Temporary works design reference, inspection frequency and hold points.
- 7
Exclusion zones, traffic routes and banksman arrangements.
- 8
Washout location, water containment/treatment and waste contractor details.
- 9
Weather contingency (frost, heat, wind/rain) and protection materials.
- 10
Named supervisor(s), headcount, roles and key emergency contacts.
HSE compliance alert
A competent person must review the RAMS against the site before work starts. Cement is corrosive: irrigate skin and eyes immediately and get medical attention where needed. Only competent, briefed people install, inspect or alter formwork and operate pumps and plant.
What Ramsgen produces
Ramsgen drafts a site-specific RAMS from the project requirements and your answers about the site. It includes:
- Project-specific hazards based on your site layout and access constraints
- Emergency plans with routes to the nearest A&E and site-specific assembly points
- Permits, inspections, and quality checkpoints aligned to your schedule
- Branded PDF exports ready for principal contractor submission
Related trades
Other RAMS templates a Concrete Works package often sits alongside.
Useful articles
Guides on concrete works RAMS and CDM 2015.
Build a RAMS for the site you are on
Ramsgen drafts a site-specific RAMS from this template and exports it as a branded PDF.